Challenge:

Develop a 63 acre parcel of un-drained land located between parcels belonging to three different developers.

Solution:

Abaci secured City of Johnston approval for financial participation of $430,000.00. Then successfully negotiated a three developer’s agreement to prorate their respective financial responsibilities and routed a sewer system that optimized the benefit for all three. The system included a 42-inch diameter storm sewer and a sanitary sewer both at depths of up to 25 feet.

 